Deck Materials Compared (2026)

On a 320 sq ft deck, the material choice alone swings the project by roughly $7,000. But the cheapest deck to build is rarely the cheapest deck to own.

MaterialInstalled $/sq ft (2026)LifespanMaintenance
Pressure-treated wood$15–$3015–25 yrsClean + stain/seal every 2–3 yrs
Composite$25–$4525–30+ yrsWash occasionally; no staining
PVC$30–$5030–50 yrsWash occasionally; best fade resistance

Pressure-treated wood: cheapest up front

The value play, and the most DIY-friendly. Downsides: annual cleaning, staining every 2–3 years ($800–$1,500 each time on a mid-size deck), plus eventual board replacement for warping, splitting, and splinters. Realistic life is 15–25 years with faithful upkeep — less if maintenance slips. Best for tight budgets, short-term ownership, or if you genuinely enjoy maintaining wood.

Composite: the long-term sweet spot

Trex, TimberTech, and Fiberon boards cost ~2x wood installed but eliminate staining forever and last 25–30+ years. Modern capped composites look convincingly like wood. Caveats: dark colors get hot in direct sun, boards need tighter joist spacing (more framing cost), and low-end uncapped composite can stain and fade. Buy capped boards from the top three brands and check the warranty terms.

PVC: maximum longevity, maximum price

Cellular PVC (AZEK-type) is impervious to moisture — the pick for poolside decks, heavy shade, and coastal air. Best color retention of the three. Downsides: highest upfront cost, can feel plasticky underfoot, and expands/contracts more with temperature swings, so installation details matter.

The 20-year math

320 sq ft deck. Pressure-treated at $22/sq ft = $7,040, plus seven stain jobs at ~$1,000 = ~$14,000 over 20 years. Mid-range composite at $35/sq ft = $11,200 with minimal upkeep = ~$12,000 over 20 years. Composite wins on total cost if you stay 10+ years — wood wins if you sell in five.

Don't forget the structure

Whatever you walk on, the frame underneath is pressure-treated lumber either way — and footings, framing, and labor are more than half the project cost. The boards are the visible third, not the whole budget.

Worked example: the same 320 sq ft deck, priced three ways

The comparison table above prices the walking surface. A real bid adds railing and a permit on top, and those lines barely change with decking material. Here is the full picture for a raised 320 sq ft deck with 52 ft of railing, using the mid-range figures from this page and the railing ranges from our deck calculator:

Line itemPressure-treatedCompositePVC
Surface and structure, installed$7,040 at $22/sq ft$11,200 at $35/sq ft$13,440 at $42/sq ft
Railing, 52 ft$1,664 wood at $32/ft$3,120 composite at $60/ft$3,120 composite at $60/ft
Permit$300$300$300
Total$9,004$14,620$16,860

Two lessons hide in that table. First, the boards are only part of the check you write: railing and permit add the same $1,964 to $3,420 to every column. Second, stairs, height, and old-deck removal are not in these totals, and on an elevated build they can add more than the gap between wood and composite. Price the whole project, not just the surface.

Resurfacing an existing deck follows the same logic with one twist: the frame is already paid for. If a contractor confirms the footings and framing are sound, new composite boards over the old structure can land near the cost of a full pressure-treated rebuild, which is why a frame inspection is worth scheduling before you fall in love with a board sample.

How to compare decking quotes, step by step

  1. Fix the design first. Same square footage, same height, same railing on every bid. A quote is only comparable when the scope is identical.
  2. Ask for the bid in lines: footings, framing, decking, railing, stairs, permit. Bundled totals hide where the money sits.
  3. Confirm the board, not just the category. "Composite" spans bargain uncapped boards and premium capped lines with 25-year fade warranties. Get the brand and product line in writing.
  4. Check the joist spacing in the bid. Composite and PVC usually need 12-inch on-center joists on diagonal layouts; if the framing line looks light, ask why.
  5. Add your ownership horizon. Staying 5 years, wood usually wins. Staying 15, run the 20-year math above with your own stain costs before deciding.

Common mistakes when choosing a deck material

Price your deck with the calculator

Also see: what drives fence & deck labor costs.